Project
Alvin ISD – Chiller Replacement Project
MLN Service provided a turnkey solution for the removal and installation of a 120-Ton Air Cooled Chiller at the Alvin ISD – Longfellow Elementary campus. This project was completed over a weekend and the scope of work included Crane/Rigging, Insulation, Pipefitting, Controls and Start-up. By utilizing MLN Service’s BuyBoard Agreement, MLN was able to complete this project with the support of Alvin ISD’s staff so that the building never lost cooling during operating hours.
-
Work Performed
HVAC
-
Project Type
Education & Research
-
Location
Alvin, TX